Maintain earth banks or stone-faced hedgebanks
£11 per 100m (one side), per year
Where it applies
Boundary
A boundary action — it's paid on the parcel's boundary features, not its area.
Eligibility conditions
- Bank at least 20m long, forming a land parcel boundary, continuous and complete
- Enter only the side(s) you manage
What you'll do
Keep earth banks or stone-faced hedgebanks (at least 20m long, forming parcel boundaries) in good repair. Check each one's condition at least once a year and carry out repairs within 12 months. A boundary action — it doesn't double-fund area actions on the same parcel.
Evidence to keep
- A written or photographic record of each bank's annual condition check
- Dated records of any repairs
- Contractor invoices, if done for you
Combining with other actions
Can share its area with every other action except:
- SFI 2026: BND1
- SFI 2024: BND1